UK North Sea : First Gas Flows from Jura less than one year and a half after discovery
Print
May 20, 08

Total announces that it has achieved first gas from its Jura field on time and on budget. Jura is situated in the Alwyn area, 100% owned and operated by Total, and comes on stream less than a year after development was sanctioned and only 17 months after discovery.

This High Pressure/High Temperature (HP/HT) field with proved and probable reserves of 170 million barrels of oil equivalent (boe) lies in block 3/15 of the UK sector of the Northern North Sea some 440 kilometres (275 miles) north-east of Aberdeen in a water depth of 113 metres. This discovery, exceptional in a mature zone, was made possible by the use of state-of-the-art technology to interpret seismic data and by the desire to maximise the potential of the Group’s assets portfolio.

Jura’s development represented capital expenditures of around 300 Million dollars. Its production is expected to ramp up to 6,5 million cubic metres of gas per day at plateau. With 6,000 barrels per day of liquids also being produced, this will give a combined total production capacity of around 50,000 boe per day. The ability to link into existing Total infrastructure has been a key factor in the Jura development coming on stream quickly.

A technology-driven development

It has been developed with 2 subsea wells connected via a new 3 kilometre tie-in to the Forvie North subsea manifold, from where gas will flow through an existing pipeline to the Total-operated Alwyn North platform.

Achieving such an ambitious fast-track execution has required a high degree of technological innovation. This includes the use of a 3 kilometre bundle assembly composed of an 8” flowline, umbilicals and two towheads incorporating all the process functions for the well controls. This bundle has been assembled at Wick in the North of Scotland and has been installed on the Jura location using subsea tow technology. The main Jura towhead is the largest ever built for a towed bundle, measuring more than 40 metres and weighting close to 500 tonnes.

The high pressure and wide temperature variations experienced in the two wells (690 bar and -60°C to 125°C) have also required the development of subsea control equipment specially designed to comply with the highest industrial safety standards, reflecting Total’s capability to apply new technologies to extend the productive life of the North Sea in a safe way and with minimum impact on the environment.

Mature areas: optimising assets’ value

Building on the Jura success, a broader exploration campaign has been launched in the area.

With Jura coming on stream, Total confirms its commitment to maintaining a high level of activity and maximising value creation in mature areas. Jura should allow Alwyn area production potential to maintain at a level close to its maximum capacity of 140,000 boe per day until the beginning of the next decade.

  JURA key figures  
  Prouved and Probable Reserves :170 millions boe  
  Capex : approximatively 300 Millions dollars  
  Start of production :20 May 2008  
  Developped in : 17 months after discovery  
  Production capacity : 50 000 boe per day  
     

History of Alwyn Area Development:

Alwyn 1987 First production  
Dunbar   1994 First production  
Ellon 1994  First production  
Grant 1998  First production  
Nuggets 2001  First production on N1, N2 and N3  
  2003  First production on N4  
Forvie 2005 First production  
  Jura 2006 Discovered   
    2008  First production  
         

Total Exploration and Production in the United-Kingdom

Total is one of the leading oil and gas producers on the UK Continental Shelf, with equity production of more than 260,000 boe per day in 2007. It continues to invest heavily and remains committed to the UK North Sea. Based in Aberdeen, Scotland, the company owns and operates a cluster of fields in the Alwyn Area of the northern North Sea, the Elgin and Franklin fields in the Central North Sea and the Otter field northeast of Shetland. The Company also operates the St. Fergus gas terminal and a gas transportation system, and has interests in a number of non-operated fields. Total also holds a significant interest in the West of Shetland frontier.

 

For further information, please contact:
Tel. : +33 (0) 1 47 44 46 99 - Fax : +33 (0) 1 47 44 68 21
 Send an e-mail to Media Relations

Send by e-mail Back to top
  
 



 Detailed map

   RSS Feed

Subscribe to Press Releases RSS feed
   E-mail Alerts

Get the latest news by e-mail
   Environment and Society

Consult the section
   Total in 2007

Consult the document
   Registration Document 2007

Download the Registration Document 2007 (pdf file)
link to legal link to site map link to glossary link to RSS Feeds link to E-mail Alerts